![]() |
|
#1
|
|||
|
|||
|
my project starts mid september and ends mid march. i want to see, what will be the overall % complete at the end of the year, as of december 31. how can i do that? i dont have any resources assigned.. everything is entered in duration only and i update it by updating percent complete when i do updates. |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Duration days changing when updating % complete | slinkster | Project | 14 | 07-17-2014 08:29 AM |
physical complete %, regular work, vs % complete
|
ketanco | Project | 1 | 06-16-2014 11:08 AM |
| Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
complete % and physical complete %
|
ketanco | Project | 3 | 05-25-2012 08:19 AM |
% Complete (Actual) vs % Complete (Should)
|
Carlos Maximo | Project | 3 | 12-06-2011 12:01 PM |