Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 07-14-2014, 08:32 AM
slinkster slinkster is offline Duration days changing when updating % complete Windows 7 64bit Duration days changing when updating % complete Office 2010 64bit
Novice
Duration days changing when updating % complete
 
Join Date: Jul 2014
Posts: 7
slinkster is on a distinguished road
Default Duration days changing when updating % complete

I am somewhat new @ project and am just learning so bare with me, team. I am using Project 2010.



So I base-lined a set of deliverable's, set the start, current and status date, updated the % comp to 10% on the first task within the deliverable group, and then hit F9 to update the project. When I did that the days on this particular task went from 12 to 14.8 days. I am still learning but was curious why project would push the duration out from 12 to 14.8 days?

Any help would be appreciated. Thank you!
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
Duration days changing when updating % complete total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Duration days changing when updating % complete baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:43 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft