![]() |
|
#1
|
|||
|
|||
|
I am somewhat new @ project and am just learning so bare with me, team. I am using Project 2010.
So I base-lined a set of deliverable's, set the start, current and status date, updated the % comp to 10% on the first task within the deliverable group, and then hit F9 to update the project. When I did that the days on this particular task went from 12 to 14.8 days. I am still learning but was curious why project would push the duration out from 12 to 14.8 days? Any help would be appreciated. Thank you! |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
| Change Resource Time vs. Duration when Updating Work column | lylel | Project | 3 | 07-23-2012 06:09 PM |
total slack not changing when changing duration
|
ketanco | Project | 1 | 02-11-2012 07:23 AM |
| updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
baseline duration of summary not updating. why
|
ketanco | Project | 1 | 12-14-2011 09:07 AM |