Looks as though what project is doing is accounting for 1.2 days completed and a remainder of 10.8 days to complete. So instead of assuming we can cram the 10.8 days in the remaining 8 days, it adds the remaining 10.8 days to the calendar. Hence moving the duration to 14.8 days and pushing the schedule out. Make sense?