Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 07-14-2014, 12:08 PM
slinkster slinkster is offline Duration days changing when updating % complete Windows 7 64bit Duration days changing when updating % complete Office 2010 64bit
Novice
Duration days changing when updating % complete
 
Join Date: Jul 2014
Posts: 7
slinkster is on a distinguished road
Default

Looks as though what project is doing is accounting for 1.2 days completed and a remainder of 10.8 days to complete. So instead of assuming we can cram the 10.8 days in the remaining 8 days, it adds the remaining 10.8 days to the calendar. Hence moving the duration to 14.8 days and pushing the schedule out. Make sense?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
Duration days changing when updating % complete total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Duration days changing when updating % complete baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:13 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft