![]() |
#1
|
|||
|
|||
![]()
I understand Physical % Complete with respect to Earned value. If I create a task with one resource that has work of 40 hours it will be scheduled for a week. If I enter completed work of 20 hours , and the Physical Progress is 25%, Earned Value will project the final cost for the resource based on 80 hours to complete the task. The % Complete will be 50% however.
What I don't see happening, is Project extending the task duration to two weeks, for the 80 hour work projection. Does Project do this, or do you have to manually increase the task work to 80 hours to get it to extend the duration? |
#2
|
|||
|
|||
![]()
Using Physical % complete is entirely manual. If based upon 20 hours of work that you are only 25% complete of the deliverable, you will need to make the adjustment your self.
Julie |
#3
|
|||
|
|||
![]()
Thanks Julie,
I believe this should be an option. Since earned value is already calculating the increased work, you should be able have Project recalculate the duration based on this. Chuck M. |
#4
|
|||
|
|||
![]()
If you wish Project to update actual and remaining duration and actual and remaining work, don't use Physical % complete. Use either % complete or % work complete.
|
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Floating task duration | dbsoccer | Project | 5 | 10-31-2013 09:10 AM |
How to have multiple blocks of duration for one task | AmezNez | Project | 3 | 10-10-2013 05:55 AM |
![]() |
branchi | Project | 1 | 08-15-2013 06:03 AM |
![]() |
ketanco | Project | 3 | 05-25-2012 08:19 AM |