![]() |
#1
|
|||
|
|||
![]()
Ok that title sucks.
Here is what I am trying to do. I have developers that work 8 an hour day, but they don't code for 8 hours in a day. So I am trying to get the timeline to represent a 6.5 hr day. I go into project options and set hours per day at 6.5 and hours per week as 32.5. However, if I put in a task of 8 hours in it still claims that the developer is finishing the task in one day. The expected result would be that they would finish it the next day. How should I be doing this? I want to avoid setting the developer at (6.5/8) 81.25% because then i have to adjust that everyplace. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
12 hour work days (shifts) | John Franklin | Project | 22 | 11-12-2013 03:19 PM |
![]() |
hanvyj | Project | 9 | 07-09-2013 07:27 AM |
![]() |
sanlen | Project | 1 | 06-25-2012 04:17 PM |
Calendar work days in advance | paol:o | Outlook | 4 | 05-27-2012 07:23 PM |
![]() |
Daria11 | Word VBA | 1 | 06-08-2011 06:54 PM |