Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 02-10-2014, 11:58 AM
altja altja is offline Windows 8 Office 2013
Novice
Calculating 6.5hr work days
 
Join Date: Feb 2014
Posts: 3
altja is on a distinguished road
Default Calculating 6.5hr work days

Ok that title sucks.

Here is what I am trying to do. I have developers that work 8 an hour day, but they don't code for 8 hours in a day. So I am trying to get the timeline to represent a 6.5 hr day. I go into project options and set hours per day at 6.5 and hours per week as 32.5. However, if I put in a task of 8 hours in it still claims that the developer is finishing the task in one day. The expected result would be that they would finish it the next day.

How should I be doing this?

I want to avoid setting the developer at (6.5/8) 81.25% because then i have to adjust that everyplace.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
12 hour work days (shifts) John Franklin Project 22 11-12-2013 03:19 PM
Calculating 6.5hr work days 36 days task at 40% effort - only "0.86 days" in resource hanvyj Project 9 07-09-2013 07:27 AM
Calculating 6.5hr work days 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
Calculating 6.5hr work days Calculating dates Daria11 Word VBA 1 06-08-2011 06:54 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:37 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft