Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 02-10-2014, 11:58 AM
altja altja is offline Windows 8 Office 2013
Novice
Calculating 6.5hr work days
 
Join Date: Feb 2014
Posts: 3
altja is on a distinguished road
Default Calculating 6.5hr work days

Ok that title sucks.

Here is what I am trying to do. I have developers that work 8 an hour day, but they don't code for 8 hours in a day. So I am trying to get the timeline to represent a 6.5 hr day. I go into project options and set hours per day at 6.5 and hours per week as 32.5. However, if I put in a task of 8 hours in it still claims that the developer is finishing the task in one day. The expected result would be that they would finish it the next day.

How should I be doing this?



I want to avoid setting the developer at (6.5/8) 81.25% because then i have to adjust that everyplace.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
12 hour work days (shifts) John Franklin Project 22 11-12-2013 03:19 PM
Calculating 6.5hr work days 36 days task at 40% effort - only "0.86 days" in resource hanvyj Project 9 07-09-2013 07:27 AM
Calculating 6.5hr work days 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
Calculating 6.5hr work days Calculating dates Daria11 Word VBA 1 06-08-2011 06:54 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:39 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft