ketanco ketanco is offline % complete by duration Windows 7 64bit % complete by duration Office 2010 64bit
Expert
% complete by duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default % complete by duration

my project starts mid september and ends mid march. i want to see, what will be the overall % complete at the end of the year, as of december 31. how can i do that?

i dont have any resources assigned.. everything is entered in duration only and i update it by updating percent complete when i do updates.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Duration days changing when updating % complete slinkster Project 14 07-17-2014 08:29 AM
% complete by duration physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
% complete by duration complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
% complete by duration % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:07 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft