#1
|
|||
|
|||
![]()
my project starts mid september and ends mid march. i want to see, what will be the overall % complete at the end of the year, as of december 31. how can i do that?
i dont have any resources assigned.. everything is entered in duration only and i update it by updating percent complete when i do updates. |
|
![]() |
||||