![]() |
#3
|
|||
|
|||
![]()
thanks, it is good way... is there any other way to do this? just for learning, otherwise this works well
i checked the task usage view and couldnt see how else it can be done. the only way i could think of was - (and i thought of it because a cumulative cost field exist in tas view), i entered durations in terms of cost , such as, if it is 7 day duration i entered $7 - just for the sake of seeing it , and not assigning any cost ofg course, i was just doing it by means of cost fields. i had no costs assigned in my project yet anyway. then i pasted the date range and cumulative cost (duration) to excel... and made a graph. the results were almost the same. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Duration days changing when updating % complete | slinkster | Project | 14 | 07-17-2014 08:29 AM |
![]() |
ketanco | Project | 1 | 06-16-2014 11:08 AM |
Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
![]() |
ketanco | Project | 3 | 05-25-2012 08:19 AM |
![]() |
Carlos Maximo | Project | 3 | 12-06-2011 12:01 PM |