Quote:
Originally Posted by OTPM
Welcome to the forum.
|
Thanks!
Quote:
Originally Posted by OTPM
First of all when you have task A as 5 days and task b as 10 days, and then mark task A as 100% complete the summary task DOES show 33% and NOT 50%, so not sure what your confusion is here.
|
Right. This is true of the standard % Complete field, but for a custom Text field I'm not sure how to do this. I want to be able to manually enter task completion percentages in the Text field, and have those values roll up to the summary tasks. However I don't want the values in this field to automatically update whenever I change the project Status Date. So a summary task percentage should be based solely on the manually-entered percentages, and the overall durations, of the tasks below it.
Quote:
Originally Posted by OTPM
Second can you post what you have done so far so we can have a look in more detail.
|
Absolutely. Though I can't post the project plan I am working with (confidential), I have attached an example. In this example, you will notice two columns:
- % Complete (Planned):
This is just the standard % Complete field, which updates automatically whenever I go to Update Project and pick a new Status Date. This functions just how I would like it to. The current status date in the Project Plan is 9/30, so the tasks' % Complete values are automatically updated accordingly.
- % Complete (Actual):
This is a Text field, in which I have manually entered percentages at the task level. (As you can see, we are behind on Example Task 2.) I would like the percentages to roll up to the summary task. Is there a better field that would accomplish this? I want to make sure it doesn't automatically update the percentages whenever I go to Update Project and pick a new Status Date.
Does that all make sense?
Thanks!