![]() |
|
#1
|
|||
|
|||
![]()
Trying to update a schedule using actual information is creating a problem.
Example; Establish a schedule and set a baseline. Complete a task, it started early, finished late and used more hours then established in the baseline. The task is NOT effort driven. When entering the actual data, project will adjust the actual hours based on the actual finish date or adjust the actual finish date based on the actual hours. This data is actual, it should not be adjusted in any way, shape or form. How do you stop this?? |
#2
|
|||
|
|||
![]()
Hi,
Have you got the "updating task status, updates resource status" option checked? This may be causing the problem if you are using resources. The way round it for the tasks is to, from the task usage view: - 1. Add the actual start date to the table and enter the actual start date. 2. On the right hand side, add the actual work row and add the actual work on the right hand side 3. Delete any future work from the work row, ie: remaining work =0 4. Set the actual finish date. This works for me so hopefully it will help you. Regards, Margaret |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Actual working hours per day | climbatron | Project | 2 | 12-17-2015 03:13 PM |
![]() |
poyns | Project | 1 | 05-27-2010 10:59 AM |
MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |
outlook versus outlook express | craig1000 | Outlook | 0 | 04-07-2010 01:52 PM |
![]() |
anthrax19888 | Word | 1 | 10-12-2009 08:09 AM |