Default Baseline versus actual data

Trying to update a schedule using actual information is creating a problem.



Example; Establish a schedule and set a baseline.

Complete a task, it started early, finished late and used more hours then established in the baseline. The task is NOT effort driven.

When entering the actual data, project will adjust the actual hours based on the actual finish date or adjust the actual finish date based on the actual hours.

This data is actual, it should not be adjusted in any way, shape or form.

How do you stop this??
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Actual working hours per day climbatron Project 2 12-17-2015 03:13 PM
Baseline versus actual data Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
outlook versus outlook express craig1000 Outlook 0 04-07-2010 01:52 PM
Baseline versus actual data Print preview and actual print do not match? anthrax19888 Word 1 10-12-2009 08:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:45 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft