#1
|
|||
|
|||
|
Hi
Welcome to the forum. First of all when you have task A as 5 days and task b as 10 days, and then mark task A as 100% complete the summary task DOES show 33% and NOT 50%, so not sure what your confusion is here. Second can you post what you have done so far so we can have a look in more detail. Tony(OTPM) |
|
#2
|
|||
|
|||
|
Thanks!
Quote:
Quote:
Thanks! Last edited by abw1987; 09-28-2011 at 06:53 AM. Reason: Clarity |
|
#3
|
|||
|
|||
|
Hi
Unfortunately this cannot be done in Project. Sorry I could not help further. Tony(OTPM) |
|
| Tags |
| actual, completion, planned |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Baseline versus actual data | Plas | Project | 1 | 12-16-2015 09:35 AM |
| Very simple / STUPID question about actual vs. planned hours | sam-sam | Project | 0 | 12-07-2010 02:55 PM |
| How can I change the colors of cells automatically based on Job Completion? | Learner7 | Excel | 0 | 07-06-2010 10:47 PM |
| MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |
auto data completion
|
Albatross | Word | 1 | 02-11-2010 11:13 PM |