Hi
Welcome to the forum.
First of all when you have task A as 5 days and task b as 10 days, and then mark task A as 100% complete the summary task DOES show 33% and NOT 50%, so not sure what your confusion is here.
Second can you post what you have done so far so we can have a look in more detail.
Tony(OTPM)
Reply With Quote
 

Tags
actual, completion, planned



Similar Threads
Thread Thread Starter Forum Replies Last Post
Baseline versus actual data Plas Project 1 12-16-2015 09:35 AM
Very simple / STUPID question about actual vs. planned hours sam-sam Project 0 12-07-2010 02:55 PM
How can I change the colors of cells automatically based on Job Completion? Learner7 Excel 0 07-06-2010 10:47 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
Planned Versus Actual Completion auto data completion Albatross Word 1 02-11-2010 11:13 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:15 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft