![]() |
#1
|
|||
|
|||
![]()
I have a 274 working day fixed duration task that currently has 5 personnel assigned to it. The personnel work various times (and days) on the task. No one is assigned 100%.
The task started on 08/31/16 and finishes on 09/29/17. I have a 6th person who will need to work 2 hrs per week over the next 12 weeks. When I add the 2 hours to resource usage for the week I receive the message "Resource assigned outside the original dates for task ..." and it extends the finish date. Any thoughts why this would occur? Thanks. |
#2
|
|||
|
|||
![]()
That message is usually an indication that there is non-working time in the resource's calendar.
|
#3
|
|||
|
|||
![]()
Thanks Julie for the reply.
The resources calendar shows availability during this time. Also when I add this resource to another fixed duration task during the same timeframe there is no error on the task. |
#4
|
|||
|
|||
![]()
Okay - let's try a bit more information. You mention that the resource is assigned to another task that overlaps. Are you creating a resource overallocation? Is your leveling set to automatic? What is the peak unit for the resource's during the overlap? What is the resource's max units?
Can you attach a picture or perhaps the file? |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
codeghi | Project | 10 | 03-01-2014 08:13 AM |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
![]() |
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
![]() |
Joeb | Project | 3 | 06-25-2012 04:18 PM |
Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |