#1
|
|||
|
|||
|
I have a 274 working day fixed duration task that currently has 5 personnel assigned to it. The personnel work various times (and days) on the task. No one is assigned 100%.
The task started on 08/31/16 and finishes on 09/29/17. I have a 6th person who will need to work 2 hrs per week over the next 12 weeks. When I add the 2 hours to resource usage for the week I receive the message "Resource assigned outside the original dates for task ..." and it extends the finish date. Any thoughts why this would occur? Thanks. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Levelling resource's units to calculate duration task
|
codeghi | Project | 10 | 03-01-2014 08:13 AM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly
|
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
|
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
How to use fixed duration, fixed work and have resources/units leveled automatically?
|
Joeb | Project | 3 | 06-25-2012 04:18 PM |
| Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |