#1
|
|||
|
|||
|
Hi,
in this simple senario M1--! ß---- task ---à! M2 M1 is a milestone, task is FS to M1 and M2 is a milestone fixed in time. How can I let the task duration ALWAYS be the duration between M1 and M2? I'd like to move M2 far in time and see the task duration getting larger. Thanks, /Stefano |
|
|