I guess that the only other way to divide tasks up would be to split them into as many parts as needed. It would make things work (as such) in a programme.


If you used Work % complete, you would be able to allocate work against each split, and then use actual start/finish to give you the correct periods. I suspect this would get complicated very quickly, but it might be the solution that most closely matches the "Best solution" for the programme.

at a more basic level (please don't take this as a criticism, I know what stats are like!) I would consider spending more time on phasing and initial programming. Dividing the works into smaller areas that are achievable would give an easier overall assessment of where you are, and a more viable method of marking work as it is completed. I split between live and tender work, and the value of a well prepared tender programme is huge when it gets to live status.
Preparation is possibly the easiest implementation to the problem, but if this isn't possible, then the multi section tasks would probably be the easiest and most effective way forward.
Reply With Quote
  #2  
Old 04-12-2016, 07:04 AM
c991257 c991257 is offline Work semi completed Windows 10 Work semi completed Office 2016
Advanced Beginner
Work semi completed
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default

I found a way to track the progress so that MS Project show which days were worked using using Task Usage, but unfortunately that doesn't help much as I can't define the level of completion for a particular day.

/Møller
Reply With Quote
  #3  
Old 04-12-2016, 07:07 AM
c991257 c991257 is offline Work semi completed Windows 10 Work semi completed Office 2016
Advanced Beginner
Work semi completed
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default

Quote:
Originally Posted by Guloluseus View Post
I split between live and tender work, and the value of a well prepared tender programme is huge when it gets to live status.
Preparation is possibly the easiest implementation to the problem, but if this isn't possible, then the multi section tasks would probably be the easiest and most effective way forward.
So you submit very detailed programmes at time of tender? We normally combine all the quantities into one lump (i.e. treat all roads as one long road) and just programme that.

I'm not sure how detailing it further would help. Would you mind elaborating?

/Møller
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Work semi completed How to track resource activity (days, off % work penjding and completed, etc.) LindaC Project 1 10-31-2015 11:55 AM
Work semi completed several task must be completed out of hours, not split proj Project 1 01-13-2012 08:38 AM
Need help with user-completed letter Rhazdel Word 0 09-10-2010 10:59 AM
How do i implement learnings from completed projects? stingy Project 0 03-18-2010 02:09 AM
Semi-flexible templates (couple of questions) mshanks Word 1 07-29-2009 06:35 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft