You are mixing and matching % complete which is a duration measurement and % work complete. In order to measure % work complete - 17% - you need to assign a resource. In order to track work on specific days - you'll need a timescaled view such as the Task Usage view.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Work semi completed How to track resource activity (days, off % work penjding and completed, etc.) LindaC Project 1 10-31-2015 11:55 AM
Work semi completed several task must be completed out of hours, not split proj Project 1 01-13-2012 08:38 AM
Need help with user-completed letter Rhazdel Word 0 09-10-2010 10:59 AM
How do i implement learnings from completed projects? stingy Project 0 03-18-2010 02:09 AM
Semi-flexible templates (couple of questions) mshanks Word 1 07-29-2009 06:35 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft