![]() |
#1
|
|||
|
|||
![]()
Hi,
I am trying to puzzle out how how to show when certain work was carried out. Let's say I have a task that takes 20 days. 5% was carried out on 01 Jan 10% was carried out on 04-5 Jan 85% remains and will be done at a later stage. How do I show when the work, i.e. the actual days, was actually carried out? BTW: I'm not using resources in the programme - only tasks. /Møller |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
LindaC | Project | 1 | 10-31-2015 11:55 AM |
![]() |
proj | Project | 1 | 01-13-2012 08:38 AM |
Need help with user-completed letter | Rhazdel | Word | 0 | 09-10-2010 10:59 AM |
How do i implement learnings from completed projects? | stingy | Project | 0 | 03-18-2010 02:09 AM |
Semi-flexible templates (couple of questions) | mshanks | Word | 1 | 07-29-2009 06:35 AM |