#1
|
|||
|
|||
|
Hi,
I am trying to puzzle out how how to show when certain work was carried out. Let's say I have a task that takes 20 days. 5% was carried out on 01 Jan 10% was carried out on 04-5 Jan 85% remains and will be done at a later stage. How do I show when the work, i.e. the actual days, was actually carried out? BTW: I'm not using resources in the programme - only tasks. /Møller |
|
|