Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 02-01-2016, 03:26 AM
c991257 c991257 is offline Work semi completed Windows 7 64bit Work semi completed Office 2013
Advanced Beginner
Work semi completed
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default Work semi completed

Hi,



I am trying to puzzle out how how to show when certain work was carried out.

Let's say I have a task that takes 20 days.
5% was carried out on 01 Jan
10% was carried out on 04-5 Jan
85% remains and will be done at a later stage.

How do I show when the work, i.e. the actual days, was actually carried out?

BTW: I'm not using resources in the programme - only tasks.

/Møller
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Work semi completed How to track resource activity (days, off % work penjding and completed, etc.) LindaC Project 1 10-31-2015 11:55 AM
Work semi completed several task must be completed out of hours, not split proj Project 1 01-13-2012 08:38 AM
Need help with user-completed letter Rhazdel Word 0 09-10-2010 10:59 AM
How do i implement learnings from completed projects? stingy Project 0 03-18-2010 02:09 AM
Semi-flexible templates (couple of questions) mshanks Word 1 07-29-2009 06:35 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft