In some cases (YES)
|
#2
|
|||
|
|||
![]()
If you have more than one team in the Text field, you're going to need to go the route of resources and full assignments.
I'd use the Group field in the Resource Sheet view and assign your 4 resources to the groups and make the assignments. In order to get assignment information (like how much work a resource is performing) you need to create the assignments. |
#3
|
|||
|
|||
![]()
It is my routine working to assign project team, but my Assistant made this mistake. Now it should have been mapped in resource sheet for work convenience.
Thanks alot for your kind favor. Regards, Arif |
#4
|
|||
|
|||
![]()
You're welcome and thanks for the feedback.
|
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Transfer the control of meeting organizer to another person | ruyzeera | Outlook | 0 | 11-20-2014 09:36 AM |
Persuade my company's marketing person to use an actual template instead of document | shansen | Word | 6 | 03-11-2014 07:09 AM |
Meeting Confirmation to Goes to Wrong Person | Keynote | Outlook | 1 | 03-02-2013 01:46 PM |
Delay email to one person in a distribution list | dixiesstar | Outlook | 0 | 09-13-2012 01:56 PM |