Thread: Role of person
View Single Post
 
Old 09-03-2015, 07:59 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The Resource Usage view will show you the number of hours an individual resource is scheduled to work. In a resource view, add a custom field and divide the resource's work by total project work.