![]() Quote:
Thanks for the reply - They're all auto scheduled - The fire test task is on 6 buildings, between 30 - 60 minutes each (4.5h in total and a 8 hour day), they're all scheduled at the beginning of the day. - The levelling settings were by day, but I set it to minutes - No messages regarding Dave, I click "Level all" and nothing happens, the little red man stays there and the bars on the chart don't move. Its the same with the Emergency Light Test, 2.5 hours a day on 18 buildings. 6 of the buildings with a light test also have the fire test. |
|
![]() |
||||