#1
|
|||
|
|||
![]()
Hi,
I have a set of recurring tasks that cover a five year period. Some of the tasks are legislative deadlines that are absolute final dates. Currently Project will choose the first working day following (i.e. the next Monday). How do I set Project to choose the first working day before this cut off, and not the first working day after? regards Guy |
#2
|
|||
|
|||
![]()
What technique did you use to create the deadline dates for the recurring tasks? (Project uses the day following what date?)
|
#3
|
|||
|
|||
![]()
Actually, your question may have provided the answer I need. I'll check it out.
To answer you, I didn't set a deadline, I set up a date for the task to recur on, based on a Government programme here in NZ. However, when I set that up I did not return to it and make it into a deadline. I'll try that and see what happens. kind regards Guy C |
#4
|
|||
|
|||
![]()
Followup - yes, it was the deadline issue. The Default was set to "Start no earlier than" rather than "Must finish on".
Thanks for the direction to head in! gc |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
filtering recurring task | pascal | Project | 0 | 05-05-2010 08:07 AM |
![]() |
BettyC | PowerPoint | 2 | 04-19-2010 02:12 PM |
Recurring Outline Slide | daviddoria | PowerPoint | 0 | 10-24-2009 09:06 AM |
Stop Future Recurring Meetings | mileskb | Outlook | 0 | 06-03-2009 04:59 AM |
Archiving recurring meetings | grfxdesigner | Outlook | 0 | 03-26-2009 03:43 PM |