Recurring tasks falling on weekends - programme for working day prior
Hi,
I have a set of recurring tasks that cover a five year period. Some of the tasks are legislative deadlines that are absolute final dates. Currently Project will choose the first working day following (i.e. the next Monday).
How do I set Project to choose the first working day before this cut off, and not the first working day after?
regards
Guy
|