Quote:
Originally Posted by JulieS
I'd first look at the Resource Usage view to see what is causing the overallocation. Clearly if Dave is only working 4.5 hours - he isn't overallocated on a day by day setting. Leveling from the Gantt view (where you see the little red men) is mostly useless - you have no idea why he's overallocated, no idea what tasks are causing the issue.
|
Ah so am I supposed to level from the resource usage view? I will have a look and try it now
ETA - OK, I went on resource view and can see day by day that Dave is red. However, he is red, even when he is only doing 0.64 days. His calendar is the standard calendar. I cant think of anything else I need to check...