Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default


Quote:
Originally Posted by JulieS View Post
I'd first look at the Resource Usage view to see what is causing the overallocation. Clearly if Dave is only working 4.5 hours - he isn't overallocated on a day by day setting. Leveling from the Gantt view (where you see the little red men) is mostly useless - you have no idea why he's overallocated, no idea what tasks are causing the issue.
Ah so am I supposed to level from the resource usage view? I will have a look and try it now

ETA - OK, I went on resource view and can see day by day that Dave is red. However, he is red, even when he is only doing 0.64 days. His calendar is the standard calendar. I cant think of anything else I need to check...
Reply With Quote
  #2  
Old 10-22-2014, 03:48 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default

OK, I think I have worked out what is wrong.

It doesn't seem to like recurring tasks.

I have put some more work in there for our painters. Painting only gets done once a year on the buildings, except for one, where its 2 days a month.

So for all the buildings needing painting, I put in the relevant duration for the year and for the odd building, a recurring tasks, once a month to the end of the year. When I levelled the 2 resources on painting, it moved everything either before or after the recurring task.

Im making the tasks just individual now, to see how they go.




If anyone else has any comments, I would appreciate it
Reply With Quote
  #3  
Old 10-22-2014, 04:47 AM
JulieS JulieS is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Recurring tasks are constrained with a Start No Earlier than constraint and also have a leveling priority of 1000 - meaning do not level. You may have more success changing the priority (add the field to the Gantt chart view) to something below 1000 - the lower the number, the more likely it is to be leveled.

You'll also want to allow tasks to be split so they will not be delayed until all of the recurring tasks are complete.

And do not use leveling hour by hour. That is what is causing the overallocations when your resource isn't working a full day. Leave it at Day by Day.
Reply With Quote
  #4  
Old 10-23-2014, 01:01 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
Recurring tasks are constrained with a Start No Earlier than constraint and also have a leveling priority of 1000 - meaning do not level. You may have more success changing the priority (add the field to the Gantt chart view) to something below 1000 - the lower the number, the more likely it is to be leveled.

You'll also want to allow tasks to be split so they will not be delayed until all of the recurring tasks are complete.

And do not use leveling hour by hour. That is what is causing the overallocations when your resource isn't working a full day. Leave it at Day by Day.
Thanks I will try these today and let you know how I get on


ETA - JulieS - you are a gem, it works perfectly, thank you so much for your help
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Programme not levelling - MSP 2013 Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
Programme not levelling - MSP 2013 MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM
Priority based levelling for split tasks having actuals proj12 Project 3 02-27-2012 06:47 AM
Programme not levelling - MSP 2013 How to copy contact list to another programme ksimmonds Outlook 2 01-13-2011 06:46 AM
Programme not levelling - MSP 2013 Recurring tasks falling on weekends - programme for working day prior guyc Project 3 09-26-2010 03:32 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:48 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft