Programme not levelling - MSP 2013
Hi
I am putting together a "planned maintenance schedule" for some buildings that the company I work for manage.
I've set a years worth of recurring tasks of 30 minutes each, on a Friday for the fire panel tests, and a years worth of recurring tasks for 2.5h each on various dates of the month fro emergency light tests (ie, some buildings have theirs on the 4th of every month, some the 20th etc).
I've assigned "Dave" to all the resources. As one would imagine, the little red man appears in the indicators column quite a bit. When I hit "level all", nothing is moved. I have (I think) tried everything, and read as many help files as I can see, and nothing seems to work.
The only thing I can do link the tasks with Finish to Start links... ie so when Friday 20/3 fire panel test in building A is done, link it to building B on Friday 20/03, then building C, then D etc and then go back to building A for Friday 27/03. This is going to take me forever and surely levelling should work whether the tasks are linked or not?
Please can someone help!?
|