Quote:
Originally Posted by JulieS View Post
A couple of questions:

Are the tasks manually or auto scheduled?
Have you created the "fire test" task for multiple buildings or only one? How many buildings are involved - more than 16?

What are your leveling settings (day by day, week by week)?

Are you getting any messages back from Project when you attempt to level Dave?
Hi

Thanks for the reply

- They're all auto scheduled
- The fire test task is on 6 buildings, between 30 - 60 minutes each (4.5h in total and a 8 hour day), they're all scheduled at the beginning of the day.
- The levelling settings were by day, but I set it to minutes
- No messages regarding Dave, I click "Level all" and nothing happens, the little red man stays there and the bars on the chart don't move.


Its the same with the Emergency Light Test, 2.5 hours a day on 18 buildings. 6 of the buildings with a light test also have the fire test.