Quote:
Originally Posted by JulieS
A couple of questions:
Are the tasks manually or auto scheduled?
Have you created the "fire test" task for multiple buildings or only one? How many buildings are involved - more than 16?
What are your leveling settings (day by day, week by week)?
Are you getting any messages back from Project when you attempt to level Dave?
|
Hi
Thanks for the reply
- They're all auto scheduled
- The fire test task is on 6 buildings, between 30 - 60 minutes each (4.5h in total and a 8 hour day), they're all scheduled at the beginning of the day.
- The levelling settings were by day, but I set it to minutes
- No messages regarding Dave, I click "Level all" and nothing happens, the little red man stays there and the bars on the chart don't move.
Its the same with the Emergency Light Test, 2.5 hours a day on 18 buildings. 6 of the buildings with a light test also have the fire test.