  #6  
Old 10-01-2014, 07:35 AM
JulieS JulieS is offline % complete by duration Windows 7 64bit % complete by duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Percent complete is a duration measurement. Percent work complete is a work measurement - as you don't have resources assigned this won't work. You can use Physical % complete but that requires:
1) pre-planning or the summary tasks will not update.
2) manual entry for each task. The update project command will not change physical % complete.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Duration days changing when updating % complete slinkster Project 14 07-17-2014 08:29 AM
% complete by duration physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
% complete by duration complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
% complete by duration % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:48 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft