Percent complete is a duration measurement. Percent work complete is a work measurement - as you don't have resources assigned this won't work. You can use Physical % complete but that requires:
1) pre-planning or the summary tasks will not update. 2) manual entry for each task. The update project command will not change physical % complete. |
|
|
|