Use the Update Project command and set the status date of 31 December. Do NOT save changes.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Duration days changing when updating % complete slinkster Project 14 07-17-2014 08:29 AM
% complete by duration physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
% complete by duration complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
% complete by duration % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft