Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #10  
Old 09-10-2014, 08:13 AM
JulieS JulieS is offline Predecessor not considered? Windows 7 64bit Predecessor not considered? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you haven't changed the overall duration then the project summary task line will not change. You must still have a task that begins on July 17.

Filter the list of tasks looking for the July 17 start date. Post the file again and I can help more readily.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
using a predecessor twice ketanco Project 2 03-07-2014 04:52 PM
Predecessor not considered? Predecessor name displayed in a text field Leah Project 7 02-07-2014 03:26 PM
Linking predecessor twice ketanco Project 1 04-06-2012 08:49 AM
MS Project 2007 Predecessor Macro dmpyne Project 1 12-14-2011 08:46 AM
Predecessor not considered? New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:06 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft