When you schedule a project from a finish date, all tasks are constrained with an As Late As Possible constraint. so even though you have a S to S link between Task 1 and Task 2, it is still constrained with ALAP. Change the constraint to ASAP and it will honor the S to S relationship.
Constraints are stronger than links.
|