Thread: [Solved] Predecessor not considered?
View Single Post
 
Old 09-09-2014, 03:25 AM
Puddlerunna Puddlerunna is offline Windows Vista Office 2010 32bit
Novice
 
Join Date: Sep 2014
Posts: 17
Puddlerunna is on a distinguished road
Default

Hi Julie,

thanks for the feedback. Good points and already integrated into the template

Now I keep having one more issue: The duration in Line 0 won't change despite me changing the durations in the subtasks. The summary task considers these changes. Hence the project start date doesn't change and the SNLT constraint alone doesn't work.
Reply With Quote