Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 03-06-2014, 12:10 PM
ketanco ketanco is offline using a predecessor twice Windows 7 64bit using a predecessor twice Office 2007
Expert
using a predecessor twice
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default using a predecessor twice

it is not possible to use one task twice, for an activity's predecessor. lets say installation of drywall and taping tasks. I want to link taping as



drywall SS + 3 day

which i do, and it is fine

but

taping also can not finish, before drywall can finish. impossible. so, how to show this? MS project doesnt let me to also put a drywall FF as a predecessor to taping

i do not and can not end up with wrong schedule anyway, as my taping can not be complete before drywall is finsih so my dates are ok but as far as showing the relationships i am asking
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
using a predecessor twice Predecessor name displayed in a text field Leah Project 7 02-07-2014 03:26 PM
Linking predecessor twice ketanco Project 1 04-06-2012 08:49 AM
using a predecessor twice arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
MS Project 2007 Predecessor Macro dmpyne Project 1 12-14-2011 08:46 AM
using a predecessor twice New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:03 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft