it is not possible to use one task twice, for an activity's predecessor. lets say installation of drywall and taping tasks. I want to link taping as
drywall SS + 3 day which i do, and it is fine but taping also can not finish, before drywall can finish. impossible. so, how to show this? MS project doesnt let me to also put a drywall FF as a predecessor to taping i do not and can not end up with wrong schedule anyway, as my taping can not be complete before drywall is finsih so my dates are ok but as far as showing the relationships i am asking |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Predecessor name displayed in a text field
|
Leah | Project | 7 | 02-07-2014 03:26 PM |
| Linking predecessor twice | ketanco | Project | 1 | 04-06-2012 08:49 AM |
arrows remain between task bars, but predecessor info disappears from task info
|
Antares | Project | 1 | 12-14-2011 09:19 AM |
| MS Project 2007 Predecessor Macro | dmpyne | Project | 1 | 12-14-2011 08:46 AM |
New to project - Predecessor Question
|
geissap | Project | 1 | 01-20-2011 10:00 AM |