Thread Tools | Display Modes |
#1
|
|||
|
|||
![]() I have noted strange thing: When my MS project schedule tasks are grouped some parameter-wise... I can see predecessorsin task information window, but when I ungroup the arrows keep staying between task bars but predecessor info disappears in task info window... What's that ? |
#2
|
|||
|
|||
![]()
Sorry, I'm not seeing this. I've opened the file you posted earlier and see Predecessor data in both the Task Information dialog and the Task form.
When I ungroup, I still see the data in both places. Check that you have the latest updates for Project 2007. Julie |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
How do I change default log-in info? | RainPure | Office | 0 | 11-15-2010 05:07 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
![]() |
freschij | Word | 1 | 06-11-2010 12:35 PM |
![]() |
stats | Project | 1 | 04-11-2010 04:12 PM |