I have noted strange thing:
When my MS project schedule tasks are grouped some parameter-wise... I can see predecessorsin task information window, but when I ungroup the arrows keep staying between task bars but predecessor info disappears in task info window... What's that ? |
|
#2
|
|||
|
|||
|
Sorry, I'm not seeing this. I've opened the file you posted earlier and see Predecessor data in both the Task Information dialog and the Task form.
When I ungroup, I still see the data in both places. Check that you have the latest updates for Project 2007. Julie |
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| How do I change default log-in info? | RainPure | Office | 0 | 11-15-2010 05:07 AM |
| how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Hidden Info in Document
|
freschij | Word | 1 | 06-11-2010 12:35 PM |
how to set up plan with no duration info?
|
stats | Project | 1 | 04-11-2010 04:12 PM |
| info on calander | newbee | Outlook | 0 | 01-27-2006 09:19 PM |