#4
|
|||
|
|||
|
Step 1 is to ensure that you have SP-2 installed to Project 2010. Check File > Help and click the link "Additional Version and Copyright Information". It should clearly say SP-2 in the resulting dialog. If it does not say SP-2, get it installed and consider installing the June cumulative update as well.
Check what options you have selected in File > Options, Advanced, Calculation options. I generally leave all unchecked. % complete is a duration measurement - so if you have split the task and hit a period of time where a resource is not working - project will reschedule the remaining work and duration around the resource's calendar. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
| Change Resource Time vs. Duration when Updating Work column | lylel | Project | 3 | 07-23-2012 06:09 PM |
total slack not changing when changing duration
|
ketanco | Project | 1 | 02-11-2012 07:23 AM |
| updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
baseline duration of summary not updating. why
|
ketanco | Project | 1 | 12-14-2011 09:07 AM |