JulieS JulieS is offline Duration days changing when updating % complete Windows 7 64bit Duration days changing when updating % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Step 1 is to ensure that you have SP-2 installed to Project 2010. Check File > Help and click the link "Additional Version and Copyright Information". It should clearly say SP-2 in the resulting dialog. If it does not say SP-2, get it installed and consider installing the June cumulative update as well.



Check what options you have selected in File > Options, Advanced, Calculation options. I generally leave all unchecked.

% complete is a duration measurement - so if you have split the task and hit a period of time where a resource is not working - project will reschedule the remaining work and duration around the resource's calendar.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
Duration days changing when updating % complete total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Duration days changing when updating % complete baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft