ketanco ketanco is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2010 64bit
Expert
critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default critical activity with floating end date

my activity B has two successors. G with SS relation, and D with FS relation



all of them are critical

so B and G are critical because of their SS relation

but finish date of B is not pushing D, there is a 1 day gap. D is pushed by something else

I checked all float dates for B and everything shows 0. I understand that Total Float is 0, but all other floats also relate to start date of B then? so although B end date has 1 day of float it doesnt mean anything?
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
critical activity with floating end date floating month prompt schroca Word 2 05-12-2014 06:32 PM
critical activity with floating end date activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
critical activity with floating end date change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
critical activity with floating end date Floating object help ic-uc Drawing and Graphics 2 12-15-2008 09:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:00 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft