#1
|
|||
|
|||
![]()
my activity B has two successors. G with SS relation, and D with FS relation
all of them are critical so B and G are critical because of their SS relation but finish date of B is not pushing D, there is a 1 day gap. D is pushed by something else I checked all float dates for B and everything shows 0. I understand that Total Float is 0, but all other floats also relate to start date of B then? so although B end date has 1 day of float it doesnt mean anything? |
|
![]() |
||||