  #1  
Old 06-14-2014, 05:22 AM
ketanco ketanco is offline critical activity with floating end date Windows 7 64bit critical activity with floating end date Office 2010 64bit
Expert
critical activity with floating end date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default critical activity with floating end date

my activity B has two successors. G with SS relation, and D with FS relation

all of them are critical



so B and G are critical because of their SS relation

but finish date of B is not pushing D, there is a 1 day gap. D is pushed by something else

I checked all float dates for B and everything shows 0. I understand that Total Float is 0, but all other floats also relate to start date of B then? so although B end date has 1 day of float it doesnt mean anything?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
critical activity with floating end date floating month prompt schroca Word 2 05-12-2014 06:32 PM
critical activity with floating end date activity id number showing together with activity name ketanco Project 1 04-08-2014 01:27 PM
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
critical activity with floating end date change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
critical activity with floating end date Floating object help ic-uc Drawing and Graphics 2 12-15-2008 09:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:12 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft