View Single Post
 
Old 06-16-2014, 06:42 AM
ketanco ketanco is offline Windows 7 64bit Office 2010 64bit
Expert
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

let me write the relations and durations of these actvities only as the rest of activities are irrelevant.
Activity B : (Dur: 2 days) (Pred: irrelevant) (Succ: G(SS), D)
Activity D : (Dur: irrelevant) (Pred: B, G) (Succ: Irrelevant)
Activity G : (Dur: 3 days) (Pred: B(ss)) (Succ: D)

and all are critical in the schedule

So as you can see, B is making G critical by affecting its start date, and Both B and G are pushing D with FS. since D is 1 day longer than B, there is a 1 day float for finishing B. So although Start of B can not move, and the program says Total Float is 0 and I understand that, still we could make B 1 day longer, and the job would not delay. but all types of floats still show 0. so does it mean, all types of floats only depend on start dates?
Reply With Quote