critical activity with floating end date
my activity B has two successors. G with SS relation, and D with FS relation
all of them are critical
so B and G are critical because of their SS relation
but finish date of B is not pushing D, there is a 1 day gap. D is pushed by something else
I checked all float dates for B and everything shows 0. I understand that Total Float is 0, but all other floats also relate to start date of B then? so although B end date has 1 day of float it doesnt mean anything?
|