#1
|
|||
|
|||
|
By default, resources are assigned at their maximum units to the task. So a two day duration task and a resource assigned at 100% (default value) will result in 16 hours of work. If you want to allow the resource two days (duration) to accomplish 3 hours of work, you'll need to initially set the task type as Fixed Duration. Enter the 2 days duration and then assign the resource with 3 hours of work. Project will calculate the Peak units necessary to spread the 3 hours of work out over 2 days. Then you may want to set the task type back to either Fixed Units or Fixed work.
|
|
| Tags |
| resources, timelines |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Resource Allocation by weeks | Treavis | Project | 1 | 02-13-2014 03:33 AM |
Resource Allocation
|
OTPM | Project | 7 | 10-05-2012 03:40 AM |
Allocation of resource
|
Tray | Project | 3 | 06-01-2012 03:09 AM |
Change resource allocation and have it update everywhere
|
TheJuke | Project | 3 | 09-01-2011 02:25 AM |
| Locking resource for over-allocation resolution | lawrencehare | Project | 1 | 06-01-2011 03:25 AM |