By default, resources are assigned at their maximum units to the task. So a two day duration task and a resource assigned at 100% (default value) will result in 16 hours of work. If you want to allow the resource two days (duration) to accomplish 3 hours of work, you'll need to initially set the task type as Fixed Duration. Enter the 2 days duration and then assign the resource with 3 hours of work. Project will calculate the Peak units necessary to spread the 3 hours of work out over 2 days. Then you may want to set the task type back to either Fixed Units or Fixed work.
Reply With Quote
 

Tags
resources, timelines



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Allocation by weeks Treavis Project 1 02-13-2014 03:33 AM
MSP 2010 Resource Allocation Resource Allocation OTPM Project 7 10-05-2012 03:40 AM
MSP 2010 Resource Allocation Allocation of resource Tray Project 3 06-01-2012 03:09 AM
MSP 2010 Resource Allocation Change resource allocation and have it update everywhere TheJuke Project 3 09-01-2011 02:25 AM
Locking resource for over-allocation resolution lawrencehare Project 1 06-01-2011 03:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:34 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft