![]() So with the help from this forum I managed to switch from DAYS to MINUTES on my timeline. My follow up to this is: Can I specify a specific time of day on my timeline for an event to happen, instead of auto calculating them with dependencies etc.? |
#2
|
|||
|
|||
![]()
Sure, you can type date and time - i would suggest using manually scheduled tasks. show the date and time through File > Options, General. Select a date format with time included.
|
#3
|
|||
|
|||
![]()
Once again, thanks. I'm starting to see a pattern in the solutions for my queries.
|
#4
|
|||
|
|||
![]()
You're welcome David. Not sure what pattern you are seeing - but as long as it is helping - so much the better.
![]() |
![]() |
Tags |
time of day, timeline |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
dsscottage | Word | 4 | 06-01-2014 01:21 AM |
Can you review status in Project from a previous time prior to "Today" | StevieMar | Project | 3 | 04-30-2014 09:42 AM |
![]() |
nhat2nhat2 | Outlook | 1 | 09-26-2011 11:10 PM |
![]() |
Jamal NUMAN | Word | 2 | 07-03-2011 03:11 AM |
![]() |
derelyth | Excel | 4 | 03-27-2011 04:31 PM |