![]() |
|
|
|
#1
|
|||
|
|||
|
I'm hoping there is a way to do this without creating individual tasks.
Scenario:
Thanks! |
|
#2
|
|||
|
|||
|
Given your dates it looks like there is no overlap.
But assuming the task in Project 1 was longer - the answer is no. Resource Leveling could stop Project 1 task - allow Project 2 to occur and then resume Project 1. But it cannot split a resource's time between multiple tasks. You'd need to edit the work per week in the Task Usage or Resource Usage view. |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Resource Allocation
|
OTPM | Project | 7 | 10-05-2012 03:40 AM |
Allocation of resource
|
Tray | Project | 3 | 06-01-2012 03:09 AM |
Change resource allocation and have it update everywhere
|
TheJuke | Project | 3 | 09-01-2011 02:25 AM |
| Locking resource for over-allocation resolution | lawrencehare | Project | 1 | 06-01-2011 03:25 AM |
Counting Weeks
|
leroytrolley | Excel | 1 | 08-18-2008 11:12 AM |