#1
|
|||
|
|||
Resources not showing 8 hrs per day
Hi,
I am using Project 2007. I set the calendar such that resources work 8 hrs a day. However, there are days when the resource shows only 2 hrs. These days are highlighted in red in the Resource Usage view. The resources have Max Units as 100%. Can someone pls tell me the reason for this? Thanks, Preeti. |
#2
|
|||
|
|||
If the task starts at the end of the day, the resource will only work 2 hours. What time does the task begin or end?
|
#3
|
|||
|
|||
Thanks Julie.
I read one of your earlier replies and realized that Project considers units and not work, in the Resource Usage view. So even though the resources are working on 2 tasks for a total of less than 8 hrs, they are shown as over allocated as they are utilizing 100% of their units for each task. Regards, Preeti. |
#4
|
|||
|
|||
Correct. Project says that if a resource is assigned to multiple tasks and the sum of the assignment units (Peak Units) is above the resource's maximum units - they are overallocated.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Resources pool showing file name | grazi | Project | 2 | 04-04-2014 11:12 AM |
Resources - only allow users to select from resources pool | grazi | Project | 1 | 04-04-2014 11:12 AM |
How to set task to be done by 4 resources each one after another? | lukusm | Project | 1 | 01-16-2012 07:21 AM |
Total Resources | 602chrislys | Project | 1 | 10-04-2010 09:04 AM |
Assigning resources. | Sergey M | Project | 0 | 01-25-2006 09:33 AM |