Resources not showing 8 hrs per day
View Single Post
04-21-2014, 06:32 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
If the task starts at the end of the day, the resource will only work 2 hours. What time does the task begin or end?